DIRT WORK FOR SOLAR ENERGY Earth movers are preparing the site of the ZSS Solar project, with the greatest area of activity to the west and northwest of the Tesla station just west of FM 276 between Rhineland and Munday, near Johnson Memorial Cemetery.
SOLAR SITE Looking north from CR 4460 in southeastern Knox County, it’s possible to observe progress with storage containers, personal vehicles, and water trucks on the ZSS Solar site; a great deal of grading work has already been initiated. The site map below indicates the boundaries (and one excluded parcel) from the reinvestment zone established in agreement with Knox County in February 2025.
ROAD BASE is being graded and watered on CR 4460, in preparation for heavy equipment to travel the road to the site entrance.
ZSS Solar construction beginse
ZSS Solar construction begins
The first of three solar farms slated for construction in Knox County has started to show some life— and blowing sand is not holding back the project.
Earth movers are on location and preparing the location. The greatest area of activity is to the west and northwest of the Tesla station just west of FM 276 between Rhineland and Munday.
Trucks have been delivering road material and roads are being co…